SB - Street Village Project
Q3 2022 - 34 people who moved in, 8 people have gotten jobs. 9 people have transitioned to stable housing. All other residents work with an Intensive Case Manager to assist in getting them to their next home.
Q3 2022 - 34 people who moved in, 8 people have gotten jobs. 9 people have transitioned to stable housing. All other residents work with an Intensive Case Manager to assist in getting them to their next home.
34 Units + Site Facilities - The Santa Barbara Street Village featured 34 residential units, along with a communal dining room, laundry facilities for all of the residents, as well as showers and four offices.
Total Build Cost $1.7M - While permanent supportive housing can cost up to $750,000+ a unit, we were able to build this community of 34 units and additional shared facilities for $1.7 million.
Highlights:
34 Units built
45 Current residents
Completed in less than 9 months
$1.7M Project Build Cost (Dignity Moves)
$1.5M Yearly Operations and Programming Costs (Good Samaritan Housing)
Total Cost (Build per unit + 1-year Service = 1-unit/1-person): $73K per person